The car park on the 2nd underground floor of the future luxury apartment building will be supported by 310lm of walls with 2,000m² of visible surface area.
Overall, the 5-person team led by a worksite manager will have set up no fewer than 560 piles (diameter: 600mm, depth: between 11 and 12m) over a 2-month period. It also set up a layer of struts (80t of steel).
Despite slight overconsumption of concrete in Bordeaux’s karstic horizons, the worksite encountered no specific issues and the struts are currently being disassembled.
Client: Vinci Immobilier
Project owner: Vinci Immobilier
General contractor: SCIB
Consortium: Stibat (carcassing), Atlas (earthworks), Franki Fondation (foundations and secant piles)